EVALUASI KINERJA WAKTU PELAKSANAAN PROYEK REKONSTRUKSI JALAN DADAP KABUPATEN TANAH BUMBU

Authors

  • Elva Shanty Widuri Prodi Teknik Sipil Fakultas Teknik Universitas Achmad Yani Banjarmasin
  • Lucky Hurun’ain Prodi Teknik Sipil Fakultas Teknik Universitas Achmad Yani Banjarmasin

DOI:

https://doi.org/10.51878/vocational.v6i4.14319

Keywords:

Earned Value Management, Kinerja Waktu, Rekonstruksi Jalan

Abstract

ABSTRACT

Road reconstruction projects require effective time control to ensure that project activities are completed according to schedule and to minimize the risk of delays that may affect project objectives. This study aimed to evaluate the time performance of the Dadap Road Reconstruction Project in Tanah Bumbu Regency, South Kalimantan, using the Earned Value Management (EVM) method through the indicators of Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), Schedule Variance (SV), Schedule Performance Index (SPI), and Time Estimated (TE). This research employed a case study with a descriptive quantitative approach using project documentation, including the Cost Budget Plan (RAB), S-Curve, and weekly project progress reports from a single road reconstruction project. The analysis was conducted by comparing actual work progress with the planned schedule to assess the effectiveness of time control throughout project implementation. The results indicated that the project achieved 100% physical progress in the 19th week of the planned 23-week duration, meaning that the project was completed ahead of the contractual schedule. A positive SV value and an SPI greater than 1 indicated satisfactory schedule performance, while the TE estimated project completion within 21 weeks, providing a more conservative estimate than the actual completion time. These findings demonstrate that the Earned Value Management method is an effective tool for evaluating and controlling project schedule performance and can support decision-making processes in infrastructure project implementation.

ABSTRAK

Proyek rekonstruksi jalan memerlukan pengendalian waktu yang efektif agar pelaksanaan pekerjaan dapat berlangsung sesuai target dan mengurangi risiko keterlambatan yang berdampak pada pencapaian sasaran proyek. Penelitian ini bertujuan mengevaluasi kinerja waktu pada Proyek Rekonstruksi Jalan Dadap, Kabupaten Tanah Bumbu, Kalimantan Selatan, menggunakan metode Earned Value Management (EVM) melalui indikator Budgeted Cost of Work Scheduled (BCWS), Budgeted Cost of Work Performed (BCWP), Schedule Variance (SV), Schedule Performance Index (SPI), dan Time Estimated (TE). Penelitian ini merupakan studi kasus yang menggunakan pendekatan deskriptif kuantitatif dengan memanfaatkan data dokumen proyek yang meliputi Rencana Anggaran Biaya (RAB), Kurva-S, serta laporan mingguan pelaksanaan pada satu proyek rekonstruksi jalan. Analisis dilakukan dengan membandingkan capaian pekerjaan aktual terhadap rencana untuk menilai tingkat efektivitas pengendalian waktu selama proyek berlangsung. Hasil penelitian menunjukkan bahwa proyek berhasil mencapai progres fisik 100% pada minggu ke-19 dari durasi rencana 23 minggu, sehingga penyelesaian pekerjaan berlangsung lebih cepat daripada jadwal kontrak. Nilai SV yang positif dan SPI lebih besar dari satu mengindikasikan bahwa pelaksanaan proyek memiliki kinerja waktu yang baik, sedangkan nilai TE memperkirakan penyelesaian proyek dalam 21 minggu sehingga memberikan estimasi yang lebih konservatif dibandingkan kondisi aktual. Temuan ini menunjukkan bahwa metode Earned Value Management efektif digunakan sebagai alat evaluasi dan pengendalian kinerja waktu proyek konstruksi serta dapat mendukung proses pengambilan keputusan dalam pelaksanaan proyek infrastruktur.

Downloads

Download data is not yet available.

References

Abshor, R. S., & Jin, O. F. (2026). Analisis perbandingan kinerja waktu proyek dengan metode earned value dan earned schedule. JMTS: Jurnal Mitra Teknik Sipil, 9(2), 535–548. https://doi.org/10.24912/jmts.v9i2.37285

Ariana, I. K. A., & Lestari, D. A. (2023). Analisis kinerja proyek optimalisasi SPAM Gatak Kabupaten Sukoharjo dengan metode earned value. Journal of Integrated System, 6(1), 87–102. https://journal.maranatha.edu/index.php/jis/article/view/6521

Aziza, W. A., Amar, T. I. K., Sahid, M. N., & Priyanto, B. (2025, June). Evaluasi kinerja waktu dan biaya menggunakan metode Time Cost Trade Off pada proyek peningkatan Jalan Ngadirojo–Giriwoyo Tahun Anggaran 2024. Dalam Prosiding Seminar Nasional Teknik Sipil UMS (hlm. 30–40). https://proceedings.ums.ac.id/sipil/article/view/5588

Elseufy, S. M., Hussein, A., & Badawy, M. (2026). A comprehensive framework for evaluating bridge project rework through earned value management (EVM) and building information modeling (BIM). Scientific Reports, 16(1), 7197. https://www.nature.com/articles/s41598-025-27546-0

Faisal, F., Ingsih, I. S., & Aasniari, A. (2025). Analisis penjadwalan proyek konstruksi dengan menggunakan metode Project Evaluation and Review Technique (PERT) dan Critical Path Method (CPM) pada proyek pembangunan Gedung Riset dan Inovasi Ilmu Komputer Universitas Brawijaya Tahap 1. Jurnal Rekayasa Sipil (e-Journal), 15(2), 311–318. https://jim.unisma.ac.id/index.php/ft/article/view/28486

Firdaus, W., & Witjaksana, B. (2023). Analisis pengendalian waktu proyek dengan metode Line of Balance (LOB) pada proyek Perumahan Central Park Middle East Ring Road. Journal of Scientech Research and Development, 5(2), 851–865. https://doi.org/10.56670/jsrd.v5i2.263

Fisabilillah, M. K., Ingsih, I. S., & Mubarok, J. (2026). Analisis implementasi metode Critical Path Method (CPM) dan Schedule Performance Index (SPI) dalam monitoring dan evaluasi pada Proyek Hotel Garuda Nusantara Malang. Jurnal Rekayasa Sipil (e-Journal), 16(1), 179–186. https://jim.unisma.ac.id/index.php/ft/article/view/30627

Hardina, N. (2022). The manajemen rantai pasok material terhadap keterlambatan pelaksanaan proyek konstruksi jalan: Kata kunci: manajemen, rantai pasok, material, keterlambatan, proyek. Jurnal Ilmiah Teknik Unida, 3(1), 49–59. https://doi.org/10.55616/jitu.v3i1.210

Henong, S. B. (2022). Dampak pandemi COVID-19 terhadap penyelesaian proyek konstruksi: Tinjauan literatur sistematis. Journal of Sustainable Construction, 2(1), 23–29. https://doi.org/10.26593/josc.v2i1.6018

Ihsan, A., & Mulyadi, M. (2025). Strategi optimalisasi manajemen proyek infrastruktur energi terbarukan untuk meningkatkan ketepatan waktu dan kualitas instalasi. Jurnal Praktik Keinsinyuran, 2(3), 254–264. https://ejournal.atmajaya.ac.id/index.php/jpk/article/view/6887

Indriani, A. M., Utomo, G., & Rizqy, M. (2022). Analisis kinerja waktu dan biaya proyek konstruksi dengan metode Earned Value Analysis. Jurnal GeoEkonomi, 13(2), 128–137. https://doi.org/10.36277/geoekonomi.v13i2.219

Liang, Y. (2025). AI-driven project management for construction SMEs: A framework for cost and schedule optimization. International Journal of Engineering Advances, 2(2), 93–100. https://www.gbspress.com/index.php/IJEA/article/view/446

Mahapatni, I. A. P. S., Putra, C., & Murwanta, K. E. (2022). Analisis kinerja waktu dan biaya pelaksanaan proyek dengan metode Earned Value pada proyek pembangunan Jembatan Pangkung Dalem Ruas Jalan Gitgit–Wanagiri. Jurnal Ilmiah Kurva Teknik, 11(2), 17–25. https://doi.org/10.36733/jikt.v11i2.5424

Pribadi, R. A., & Abduh, M. (2022). Analisis Cost Performance Index (CPI) dan Schedule Performance Index (SPI) menggunakan metode Earned Value (Studi kasus pada proyek pembangunan Gedung Pasar Bucor Kulon Kabupaten Probolinggo). Media Teknik Sipil, 20(1), 14–23. https://doi.org/10.22219/jmts.v20i1.14620

Purwantoro, A., Suhin, K. J., & Nuswantoro, W. (2022). Pengendalian proyek konstruksi gedung menggunakan Critical Path Method (CPM) dan Earned Value Method (EVM). Jurnal Teknika: Jurnal Teoritis dan Terapan Bidang Keteknikan, 5(2), 65–72. https://e-journal.upr.ac.id/index.php/JT/article/view/7651

Rahmanto, T., & Janizar, S. (2022). Pengendalian biaya dan waktu dengan metode earned value proyek Familia Urban Bekasi. Jurnal Teknik Sipil Cendekia (JTSC), 3(2), 331–342. https://doi.org/10.51988/jtsc.v3i2.48

Sheikhalishahi, M., Abdolhossein Zadeh, S., Naeimi, S., & Sardardabadi, A. (2022). Improving earned value management and earned schedule by statistical quality control charts considering the dependence between cost and schedule. Journal of Quality Engineering and Production Optimization, 7(1), 177–198. https://doi.org/10.22070/jqepo.2022.15415.1215

Sholahuddin, M., & Saputra, I. H. (2024). Penerapan earned value management (EVM) sebagai upaya pengendalian kinerja biaya dan waktu pelaksanaan pada pekerjaan infrastruktur jalan. Innovative: Journal of Social Science Research, 4(5), 3353–3366. https://doi.org/10.31004/innovative.v4i5.14896

Sukindrawati, B., & Kartika, W. (2023). Evaluasi kinerja waktu dengan metode konsep nilai hasil. Jurnal Menara, 18(2). https://doi.org/10.21009/jmenara.v18i2.36648

Usman, S., Muhammad, A. H., Adjam, I., & Altarans, I. (2023). Optimasi biaya dan waktu pelaksanaan proyek konstruksi dengan penambahan jam kerja dan penambahan tenaga kerja menggunakan metode Time Cost Trade Off (Studi kasus: Proyek Pembangunan Gedung Islamic Center Halmahera Tengah). DINTEK, 16(1), 17–31. https://jurnal.ummu.ac.id/index.php/dintek/article/view/1484

Ximenes, F. F. (2025). Analisis waktu dan biaya dalam pengendalian proyek konstruksi menggunakan metode earned value: Studi kasus proyek Gedung UNTL. Axial: Jurnal Rekayasa dan Manajemen Konstruksi, 13(1), 11–20. https://doi.org/10.30742/axial.v13i1.4333

Yogi, M. R. A., Berawi, M. A., Latief, Y., & Sucahyo, Y. G. (2026). Construction task priority development using genetic algorithm: A numerical approach for progress and resource allocation. Journal of Soft Computing in Civil Engineering, 10(1), e1948. https://www.jsoftcivil.com/article_232361.html

Downloads

Published

2026-08-07

How to Cite

Widuri, E. S., & Hurun’ain, L. (2026). EVALUASI KINERJA WAKTU PELAKSANAAN PROYEK REKONSTRUKSI JALAN DADAP KABUPATEN TANAH BUMBU. VOCATIONAL: Jurnal Inovasi Pendidikan Kejuruan , 6(4), 532–542. https://doi.org/10.51878/vocational.v6i4.14319

Issue

Section

Articles