ANALISIS PRODUKTIVITAS TENAGA KERJA DITINJAU DARI IDLE TIME PADA PEKERJAAN STRUKTUR ATAS PROYEK KONSTRUKSI GEDUNG HEALTH SCIENCE UNIVERSITAS AIRLANGGA
DOI:
https://doi.org/10.51878/cendekia.v6i3.11834Keywords:
Produktivitas, Idle Time, Akar MasalahAbstract
Labor productivity is one aspect that can determine the success of a construction project. This study aims to analyze labor productivity in terms of idle time and identify the contributing factors in the Airlangga University Health Science Building Construction Project. Data collection was conducted using continuous observation methods, a labor perception questionnaire, and in-depth interviews with project structural staff. Identification of the contributing factors to idle time was conducted using a data integration approach, a fishbone diagram, and a 5 Whys analysis to explore the root cause. The results of the study showed that the actual productivity of labor in column reinforcement work was 2,60 kg/person-hour, beam reinforcement was 5,80 kg/person-hour, plate reinforcement was 2,65 kg/person-hour, column formwork was 2,39 m²/person-hour, beam formwork was 0,30 m²/person-hour, plate formwork was 0,67 m²/person-hour, column casting was 0,66 m³/person-hour, and beam and plate casting was 0,18 m³/person-hour. Overall, the labor had a productive time of 68.29% and idle time of 31.71%, which is categorized as "good" based on the standard (Oglesby, 1989). Based on the results of data integration, fishbone diagrams, and 5 Whys analysis, it was found that the dominant factor causing idle time in the man category was labor fatigue, in the methods category was lack of communication, in the machine category was limited availability of tools, in the material category was the adequacy of ready-to-install materials in the field, and in the eksternal category was weather factors. All of these factors are chain impacts rooted in the limited project land because it is located in an active campus area, thus causing operational management to be unprepared in adapting to environmental and weather conditions.
ABSTRAK
Produktivitas tenaga kerja merupakan salah satu aspek yang dapat menentukan keberhasilan dalam proyek konstruksi. Penelitian ini bertujuan untuk menganalisis produktivitas tenaga kerja ditinjau dari waktu tidak produktif (idle time) serta mengidentifikasi faktor-faktor penyebabnya pada Proyek Konstruksi Gedung Health Science Universitas Airlangga. Pengumpulan data dilakukan menggunakan metode continuous observation, kuisioner persepsi tenaga kerja dan wawancara mendalam (deep interview) kepada staf struktural proyek. Identifikasi faktor penyebab idle time dilakukan menggunakan pendekatan integrasi data, diagram tulang ikan, serta analisis 5 whys untuk menelusuri akar masalah. Hasil penelitian menunjukkan bahwa produktivitas aktual tenaga kerja pada pekerjaan pembesian kolom sebesar 2,60 kg/jam-orang, pembesian balok sebesar 5,80 kg/jam-orang, pembesian pelat sebesar 2,65 kg/jam-orang, bekisting kolom sebesar 2,39 m²/jam-orang, bekisting balok sebesar 0,30 m²/jam-orang, bekisting pelat sebesar 0,67 m²/jam-orang, pengecoran kolom sebesar 0,66 m³/jam-orang, serta pengecoran balok dan pelat sebesar 0,18 m³/jam-orang. Secara keseluruhan, tenaga kerja memiliki waktu produktif sebesar 68,29% dan idle time sebesar 31,71%, yang dikategorikan "baik" berdasarkan standar (Oglesby, 1989). Berdasarkan hasil integrasi data, diagram tulang ikan, dan analisis 5 Whys, ditemukan bahwa faktor dominan penyebab idle time pada kategori man adalah kelelahan tenaga kerja, pada kategori methods adalah kurangnya komunikasi, pada kategori machine adalah keterbatasan ketersediaan alat, pada kategori material adalah kecukupan material siap pasang di lapangan, dan pada kategori eksternal adalah faktor cuaca. Seluruh faktor tersebut merupakan dampak berantai yang berakar pada keterbatasan lahan proyek karena berlokasi di kawasan kampus aktif, sehingga menyebabkan ketidaksiapan manajemen operasional dalam beradaptasi terhadap kondisi lingkungan dan cuaca.
Downloads
References
Ardi, F., Wanandy, K. C., & Alifen, R. S. (2015). Produktivitas Pekerja pada Pekerjaan Beton Bertulang Proyek Bangunan Bertingkat (Studi Kasus Proyek Bangunan Condominium TP6). Jurnal Dimensi Pratama Teknik Sipil, 4(2). https://publication.petra.ac.id/index.php/teknik-sipil/article/view/3893
Brioso, X., & Calderon-Hernandez, C. (2023). Framework for integrating productive, contributory, and noncontributory work with safe and unsafe acts and conditions. International journal of environmental research and public health, 20(4), 3412. https://doi.org/10.3390/ijerph20043412
Diana, V. S. (2022). Perbandingan produktivitas pekerja di lapangan dengan Permen PUPR 2022 pada proyek Guest House Exindo 57 Kabupaten Nganjuk. Jurnal Extrapolasi, 19(1), 26–34. https://doi.org/10.30996/ep.v19i01.6695
Dozzi, S. P., & Abourizk, S. M. (1993). Productivity in construction. National Research Council Canada.
Rohman, M. F. A. (2026). Analisis faktor yang mempengaruhi produktivitas tenaga kerja pada pekerjaan struktur renovasi gedung gpp 5 menjadi dapur sehat anak bangsa di malang. JUMATISI: Jurnal Mahasiswa Teknik Sipil, 7(1), 20-27. https://doi.org/10.24127/jumatisi.v7i1.9780
Faustine, C., & Waty, M. (2022). Peringkat Faktor-Faktor Yang Mempengaruhi Produktivitas Tenaga Kerja Pada Proyek Konstruksi. JMTS: Jurnal Mitra Teknik Sipil, 681-692. https://journal.untar.ac.id/index.php/jmts/article/view/20247
Guo, S., & Asce, M. (2002). Identification and resolution of work space conflicts in building construction. Journal of Construction Engineering and Management, 128(4), 287–295. https://doi.org/10.1061/(ASCE)0733-9364(2002)128:4(287)
Irpan. (2021). Analisa produktivitas pekerja dengan metode time study pada proyek pembangunan Gedung Rumah Sakit Pertamina Tarakan. Jurnal Borneo Saintek, 4(2). https://doi.org/10.35334/borneo_saintek.v4i2.2157
Karima, B. R., Khamim, M., & Setiono, J. (2020). Analisa produktivitas tenaga kerja berdasarkan Permen PUPR dan perhitungan lapangan pekerjaan beton bertulang Proyek Apartemen Bess Mansion. Jurnal Online Skripsi Manajemen Rekayasa Konstruksi (JOS-MRK), 1(2), 19-25. https://doi.org/10.55404/jos-mrk.2020.01.02.19-25
Kim, J. W., Ham, N., & Kim, J. J. (2021). Quantitative analysis of waiting length and waiting time for frame construction work activities using a queue model; focusing on Korean apartment construction. Sustainability, 13(7), 3778. https://doi.org/10.3390/su13073778
Koehn, E., & Brown, G. (1985). Climatic effects on construction. Journal of Construction Engineering and Management, 111(2), 129–137.
Malamassam, L. (2016). Time study pada proyek pembangunan gedung: Study method on its industrial engineering. Institut Teknologi Sepuluh Nopember.
Oglesby, C. H. (1989). Productivity improvement in construction. McGraw-Hill.
O’Neill, T. A. (2017). An overview of interrater agreement on Likert scales for researchers and practitioners. Frontiers in Psychology, 8, Article 777. https://doi.org/10.3389/fpsyg.2017.00777
Parjaman, T., & Akhmad, D. (2019). Pendekatan penelitian kombinasi: sebagai “jalan tengah” atas dikotomi kuantitatif-kualitatif. Moderat: Jurnal Ilmiah Ilmu Pemerintahan, 5(4), 530-548. https://jurnal.unigal.ac.id/moderat/article/view/3077
Prasetyo, I., Dani, H., & Zulfikar, R. (2025). Factors influencing construction worker productivity in Indonesia and strategies for improvement. Multidisciplinary Science Journal, 8(4), 1–10. https://doi.org/10.31893/multiscience.2026243
Cahyadi, H., Purnamasari, E., & Nordiansyah, M. (2021). Perhitungan Produktivitas Pekerjaan Pemasangan Dinding Bata Ringan dengan Metode Time Study pada Proyek Pembangunan Ruang Kantor Sekolah Menengah Atas Negeri 5 Banjarmasin. PROSIDING SNITT POLTEKBA, 5, 37-43. https://jurnal.poltekba.ac.id/index.php/prosiding/article/view/1342
Wijaya, G. A., Sucita, I. K., & Saputra, J. (2021). Analisis tingkat dan faktor produktivitas tenaga kerja pada pekerjaan struktur atas di proyek X. Portal: Jurnal Teknik Sipil, 13(2). https://doi.org/10.30811/portal.v13i2.2336
Belladona, M., Antoro, E. D., & Sandra, A. (2019). ANALISIS PRODUKTIVITAS TENAGA KERJA PADA PEKERJAAN BETON BERTULANG MENGGUNAKAN METODE TIME STUDY:(Studi Kasus: Proyek Pembangunan Rumah Sakit Gading Medical Bengkulu). Majalah Teknik Simes, 13(1), 6-17. https://journals.unihaz.ac.id/index.php/simes/article/download/1723/916
Kombong, E. P. (2025). Analisis Produktivitas Tenaga Kerja Pada Pekerjaan Pile Cap Menggunakan Macro VBA. Jurnal Komposit, 9(1), 115-125. https://ejournal.uika-bogor.ac.id/index.php/komposit/article/view/16587/6224